Transmission Services
Business Practices & Tariffs You must have Adobe® Acrobat Reader® on your computer to view these documents. If you do not have the Adobe Acrobat Reader, you may download it for free from the Adobe Web site. Business Practices Cleco OASIS Business Practices Business Practice Update Policy Unreserved Use Principles Imbalance Service Principles Tariffs Cleco Power Open Access Transmission Tariff Cleco Power OASIS Web site Transmission Service Request System Impact Study & Facilities Study Procedures The following outlines the current policy of Cleco Power LLC regarding System Impact and Facilities Studies as defined in Cleco's currently filed Open Access Transmission Tariff, OATT.
This policy shall remain in affect until such time Cleco sees fit to modify it, in a non-discriminatory fashion, due to, among other things, better accommodate the marketplace, eliminate abuses to the process, further explain/clarify the process, or reflect changes to the OATT itself. These policies only are associated with requests for transmission service and are in no way related to the system interconnection process.
Definition As defined by the Cleco OATT itself, both a Facilities Study and System Impact Study are engineering analyses executed by a transmission provider in response to a request for transmission service. More precisely, the Cleco OATT defines these studies as follows:
System Impact Study - An assessment by the transmission provider of (i) adequacy of the transmission system to accommodate a request for either firm point-to-point transmission service or network integration transmission service and (ii) whether any additional cost may be incurred in order to provide transmission service.
Facilities Study - An engineering study conducted by the transmission provider to determine the required modifications to the transmission provider's transmission system, including the cost and scheduled completion date for such modifications, that will be required to provide the requested transmission service.
System Impact and Facilities Study Process Manual Summary of Procedures Based on a valid transmission service request for firm or network service, the following summarizes the process. System Impact Study The process:
- Request/inquiry for serviced received
- Transmission Provider must contact customer within 30 days to either (i) grant service or (ii) inform customer a System Impact Study is required.
- Customer must execute System Impact Study Agreement within 15 days else it is deemed withdrawn
- System Impact Study completed (or extension requested) within 60 days
- Study posted on OASIS
- Customer provided results and has 15 days to sign Service Agreement if no Facilities Study needed due to upgrades/additions; else request deemed withdrawn
- Customer billed
Facilities Study If as a result of the System Impact Study transmission upgrades/additions are necessary, a Facilities Study is necessary and shall be conducted as follows: - Facilities Study Agreement tendered to customer within 30 days of System Impact Study Completion
- Customer executes Facilities Study Agreement within 15 days else request is deemed withdrawn
- Facilities Study to be completed within 60 days unless extended
- Results posted on OASIS
- Results provided customer
- Customer has 30 days to execute Service Agreement else request deemed withdrawn
Completed System Impact Studies
Request System Impact Studies and Facilities Studies performed before September 2007 by e-mail or mail. Click Contact Us and select Interconnections and OATT Business to send your request via e-mail. To request by mail, send your return address, phone number and transmission service request number to the address below. c/o Cleco Transmission Operations Center 2180 St. Landry Highway P.O. Box 70 St. Landry, La 71367 Find studies conducted after September 2007 on the Cleco Power OASIS node.
Transmission Interconnections (Wholesale Customers)
Wholesale customers requesting to interconnect and take transmission service on the Cleco Power transmission system shall make a Transmission Service Request (TSR) on the Cleco Power OASIS Web site. The document Transmission Service Request System Impact Study and Facilities Study Process Manual for Cleco Power LLC defines the business practices for conducting System Impact Studies and Facilities Studies. To avoid impacts to the transmission system reliability facility interconnection and performance requirements have been established for all wholesale customers interconnecting to the transmission system (69kV and above) and can be found in the document Requirements for Transmission System Interconnections for Generation, Transmission and End-User.
End-User Interconnections (Retail Customers)
Retail customers requesting to interconnect to the Cleco Power transmission system shall contact the Manager of Large Account Management. Mike Campbell 318-484-7549 The manager will assign an account representative to act as a liaison between the customer and Cleco Power. The account representative will initiate confidentiality agreements between Cleco Power and the customer and provide assistance to ensure all procedures and requirements are followed. To avoid impacts to the transmission system reliability facility interconnection and performance requirements have been established for all retail customers interconnecting to the transmission system (69kV and above) and can be found in the document Requirements for Transmission System Interconnections for Generation, Transmission and End-User.