Skip to Navigation Skip to Main Content Skip to Footer
 

Cleco Restores More than Half of Isaac Outages

Aug 31, 2012

PINEVILLE, La., August 31, 2012
8/31, 6 a.m. Update    

Cleco was able to restore power to 52 percent of customers affected by Hurricane Isaac and completed restoration in Acadia, Evangeline, LaSalle and St. Landry parishes on the first day of the recovery effort.  The work of 2,400 employees and contractors continues today in rainy conditions throughout central and southeastern Louisiana.

Current Outage/Restoration Count
Avoyelles Parish – 210 
Evangeline Parish – 1 
Grant Parish – 50 
Iberia Parish – 201 
Rapides Parish – 471 
St. Martin Parish – 18 
St. Mary Parish – 1,737 
St. Tammany Parish – 41,853 
Washington Parish – 771

TOTAL 45,314